Road Reconstruction - Evan Street, Belmont

We’re upgrading Evans St from Roslyn Rd to Torquay Rd as part of the Federal Government’s Roads to Recovery Program.   
Roadworks likely to commence early September 2024.

What we are doing 

We are upgrading Evans St, Belmont as part of the Federal Government commitment to improve our road network.
The project is funded by the Australian Government’s Roads to Recovery Program and will include

  • Road pavement reconstruction
  • Kerb and Channel upgrades
  • Driveway upgrades
  • Line marking upgrades

This program supports local government through construction and maintenance of our local road network which facilitates greater accessibility and improves safety for our entire community.

Work times 

The works are being carried out by the City’s Construction Unit. During the road works, the road will be closed for all vehicles including resident’s vehicles. Works will commence from September 2024 and run to December 2024.

Residents and businesses who may be impacted by the works will be notified of the start date closer to commencement.

Works will occur Monday – Friday, 7am until 4pm, weather and COVID-19 restrictions permitting. Weekend work will only be required if weekdays are lost to inclement weather or unforeseeable circumstances.

Traffic impacts

For the safety of drivers and our staff, the road will be closed during the proposed timeframes as mentioned above. Appropriate traffic detours will be put in place to help manage traffic flow. Residents in these work zones will have pedestrian access to their properties only. We will endeavour to minimise the disruption while the works are being undertaken.

Emergency services 

We have notified local emergency service providers about the works. Traffic control staff will be on site to allow access for emergency vehicles if required during working hours.

Rubbish collection

Rubbish bins will be collected at either end of the work zone stage following regular collection schedule. Please ensure bins are suitably located the night prior to collection. Alternatively, Council crews will move bins into position for collection on behalf of residents living inside the construction zone. Then they’ll be return once emptied.