Green Spine Works Update - Week commencing 12 February 2018

Wednesday, 14 February 2018

Works underway this week commencing 12 February 2018

  • Continue footpath demolition, undertaken as night works (see hours of work). Footpath demolition is due for completion this week. Specific locations of demolition works may vary during the week subject to progress and site requirements. Businesses will be individually notified prior to demolition works in their immediate area.
  • During the day, excavators will be working behind the barriers, between the footpath and the roadway kerb.
  • Trucks will be on site to remove excavated materials.
  • Preparation of rock sub-base for concrete will be undertaken as night and day works (see hours of work).
  • Concrete works are scheduled to commence early this week from the Yarra Street end of Malop Street, working towards the entry to Westfield shopping centre. Access to Anytime Fitness and Myer will be maintained during their trading hours.
  • Continue trenching to install services including irrigation and electrical.
  • Continue stormwater works.

Pedestrian access

Pedestrian access to businesses will be maintained during all trading hours. If access is required outside your normal trading hours, please contact the construction Site Manager with as much notice as possible, so access can be facilitated.

A pedestrian link between Market Square and Westfield shopping centres will continue to be available for all trading hours during the works.


Vehicle access

Two-way vehicle traffic will be maintained in Malop Street between Moorabool and Yarra Streets during footpath works until road reconstruction work commences in March.


Hours of work

Our work crews will be on site:

Day shift: Standard day shift hours for the project will be from 7:00am to 5:00pm, Monday to Saturday unless notified otherwise.

On industry RDOs, there will be less activity on site.
Night shift: Night shift hours will continue for the duration of the footpath works.

Standard night shift hours will be from 5:00pm to 7:00am, Sunday through to Thursday, however this may extend to Friday and Saturday nights if circumstances require.

Starting times will be amended to cater for late night trading on those nights.


On site contact – Site Manager

For any immediate works-related enquiries, please contact the 2Construct Site Manager, Michael Waldron on 0403 719 925.


Questions?

If you have any questions or concerns, please contact either:

David Jarwood 0413 288 403 djarwood@geelongcity.vic.gov.au
Martelle McCleland 0428 897 323 mmccleland@geelongcity.vic.gov.au

or come past The Workshop at 108 Moorabool Street.