The Laneways Project Works Update

Friday, 14 July 2017 4:51 PM

Week of 17 July – Weekly Look Ahead

Lt Malop Street – Moorabool Street end
Services and in-ground works are complete.

Works at the Moorabool Street end of Lt Malop Street during the week will include:

  • Excavation of foundations for structures

  • Preparation for concrete slab

  • Pouring concrete

  • Final removal of fish lights.

     

Lt Malop Street – Gheringhap Street end

Services and in-ground works are complete.

Works at the Gheringhap Street end of Lt Malop Street during the week will include:
           

  • Commence concrete works

  • Concrete pouring – traffic management in place to control vehicle access, some delays expected.

James Street
West side of James Street to be fully paved before commencing east side.

Works on the west side of James Street during the week will include:

  • Continue demolition and commence service installation
Parking, pedestrian and vehicle access will be maintained on the east side. Door access to shops will be maintained. Access to John Street (north) from James Street is closed until further notice.

 

Hours of work
Crews will be on site from Monday 17 July – Saturday 22 July, between 7am – 4pm.

Access
A clearly marked 1.2m wide walkway will be maintained for pedestrians in front of all shops on Lt Malop Street. Pedestrian access to James Street west doorways (from James Street Bakery to the Lt Malop Street corner) will be maintained and accessed from the eastern footpath. Vehicle access will be maintained from Gheringhap St down Lt Malop Street and James Street. Some delays may be experienced. Traffic management will be in place.

Shorts Place

Road and footpath demolition on the west side of Shorts Place North is completed.

Works in Shorts Place during the week will include:

  • Continue building of the road in Shorts Place North

  • Finishing services installation

  • Commencing construction of footpaths.

Access

  • There continues to be limited access for pedestrians in Shorts Place

  • Half the road will be maintained for delivery access

  • The loading zone in Shorts Place North will not be available for use during resurfacing works. There are alternate loading zones located in Shorts Place South.

 

McLarty Place

Paving and asphalting has now been completed. Street furniture will be installed in the coming weeks.