Monday, 17 May 2010 2:19 PM City News, Department Updates

  • The gym and administration areas are almost complete with gym flooring being laid soon. 
  • The two theme park style waterslides have arrived from Canada and will be stored temporarily while works continue on the rest of the wintergarden. 
  • All pool shells are complete and are now being tiled, the concourse areas, hydro pool and spa are almost finished and the wintergarden water play area is underway. 
  • Installation of the waterslide tower will commence soon.
  • Construction is expected to be completed end July. A few weeks have been allowed for equipment set up, filling the pool, staff training and water testing before the centre opens its doors in August.